From a blank sheet to an FAA LOA in seven months.
Infinity Flight Group needed a multi-engine trainer to match its newest Piper PA-44 Seminoles. We designed, built, certified and installed the SOLO PRO SEMINOLE across three US training sites, on schedule, with the FAA in the loop.
- 7 monthsKick-off to LOA
- 3 sitesFlorida · New Jersey · Vermont
- 21 Jul 2026FAA evaluation
- 6 Aug 2026LOA issued
- Client
- Infinity Flight Group, flight training network, United States
- Aircraft
- Piper PA-44 Seminole, latest model: Garmin G1000 NXi, fuel-injected engines
- Device
- SOLO PRO SEMINOLE, FAA AATD
- Locations
- Fort Pierce, Florida · Trenton–Mercer Airport, New Jersey · Burlington, Vermont
- Scope
- Custom design, engineering, software and flight model, FAA certification, delivery, installation and operator training
- Also delivered
- Additional SOLO PRO G1 units for the single-engine fleet
- Outcome
- FAA Letter of Authorization (AATD) issued on 6 August 2026
A multi-engine trainer that didn’t exist yet.
Infinity Flight Group already trained on SOLO PRO G1 simulators at its locations in Fort Pierce, Florida, at Trenton–Mercer Airport in New Jersey, and in Burlington, Vermont. Its multi-engine syllabus was a different story: the school flies the latest Piper PA-44 Seminoles, with Garmin G1000 NXi avionics and fuel-injected engines, and Virtual Fly had no design for the aircraft.
In January 2026 we started a custom project to build one: a Seminole trainer faithful enough to the real aircraft to qualify as an FAA AATD. Infinity ordered SOLO PRO SEMINOLE units for all three locations, together with additional SOLO PRO G1s for its single-engine fleet.

The work that happens before kick-off.
Before we sent Infinity a proposal, our team had already completed the steps every project goes through before it is accepted. By the time Infinity said yes, every stage of development was mapped and sequenced, which is why the project ran as planned.
Feasibility study
Confirming the aircraft, its avionics and the AATD qualification target could be met.
Cost analysis
Costs assessed in full before the proposal was issued.
Project plan
Every stage mapped, from engineering and certification to delivery and evaluation.
Seven months, mapped from day one.
- 1Early JanuaryProject kick-off
- 2Mid-JuneDevices delivered, installation and training on site
- 3End of JuneFAA sets the evaluation date
- 421 JulyFAA evaluation at Trenton–Mercer Airport
- 56 AugustLetter of Authorization issued

Engineered, then flown against the book.
Detailed engineering and software development ran from the first week of January. In parallel, our FSTD certification team prepared the technical and qualification documentation needed to open the FAA AATD approval process.
Hardware assembly for every unit began at the end of March and was complete by mid-May, when hardware–software integration started: work we had been preparing for months. At the same time we tuned the PA-44 flight model in X-Plane 12, not only to meet the FAA standard but to minimise any gap between the aircraft’s POH performance data and its behaviour in the simulator, checked through our own performance tests.
May and June closed integration, followed by final quality-assurance checks and FAA preparation tests.
- AvionicsGarmin G1000 NXi
- Flight modelX-Plane 12 PA-44, tuned to POH data
- QualificationFAA AATD
Delivered, installed and tuned on site.
The simulators were delivered in mid-June, and our team travelled to Infinity to install them and train its operators.
On site we refined the flight model further, added the failure scenarios Infinity asked for, and built custom modules so that every one of its SOPs and failure scenarios can be trained and tested.

Evaluated at Infinity’s own Trenton–Mercer site.
At the end of June the FAA scheduled the evaluation for 21 July at Trenton–Mercer Airport, one of the locations where Infinity runs its SOLO PRO SEMINOLE, to confirm the device met every AATD requirement for a Letter of Authorization.
Our FSTD Certification Manager, Nil Heinz, flew to Trenton the day before to brief Infinity’s team on the process and to fine-tune the simulator with Infinity’s Chief Pilot, who flew the evaluation as test pilot.
The evaluation was completed successfully, and the FAA issued the Letter of Authorization on 6 August 2026.
One team, end to end.
Seven months from kick-off to LOA, with a regulator in the loop and no delays. The project drew on every part of Virtual Fly.
Manufacturing
Structures, panels and controls built in-house.
Software
Flight model, integration and custom failure modules.
Certification
Documentation, FAA preparation and evaluation support.
Project planning
Feasibility, costing and a mapped schedule before kick-off.
Customer support
Installation, operator training and on-site refinement.
Inside the SOLO PRO SEMINOLE.






The devices Infinity flies today.